Crystal City/Pentagon City/Potomac Yard Transportation Update
Transitway Extension Project Update

Having trouble viewing this email? View it as a Web page.

Transportation Header

Crystal City/Pentagon City/Potomac Yard Transportation Update

June 17, 2026


Visit the My Arlington map to learn about other projects in your area


Transitway Extension Project Update

TETPC - Crystal Drive Paving

Paving for Bus-Only Lanes

On Thursday, June 18, the Transitway Extension project will repave and install new markings to convert Crystal Drive and 12th Street South between South Clark Street and 15th Street South to bus-only lanes.

 

Parking lanes on the northbound side of Crystal Drive/12th Street South will be permanently removed. (Street parking was previously temporarily reinstated during Phase 2 construction of the Transitway project, with the promise that it will close again closer to bus service implementation.)

 

The project is also installing new street marks on 12th Street South from South Eads Street to South Hayes Street to convert lanes for bus-only travel.

Next Stop - Transit Improvements

As the Transitway project nears completion, 12th Street South will reopen between South Fern Street and South Eads Street. In its new configuration, the center lanes will be designated for bus travel, with two new transit stations to serve passengers with shelters, benches, and real-time arrival information.

 

After the project is completed, WMATA will redirect the northbound Metrobus A1X via Crystal Drive and 12th Street South to Pentagon City. The southbound service to Braddock Road Metro will continue on South Hayes Street, Army Navy Drive, and South Eads Street until the neighboring 15th Street/Clark-Bell Street Realignment project is complete.